Current page location:HOME > Company > Offices > SAKAI REFINERY

Site Profile(as of march 31, 2011)
Capacity of Major Equipment |
| Topping Unit |
100,000 |
barrels / day |
| Vacuum Distillation Unit |
45,000 |
barrels / day |
| Catalytic Reforming Unit |
8,000 |
barrels / day |
| Reformate Splitter |
10,000 |
barrels / day |
| Naphtha Hydrodesulfurization Unit |
11,000 |
barrels / day |
| Kerosene Hydrodesulfurization Unit |
15,000 |
barrels / day |
| Gas Oil Hydrodesulfurization Unit |
17,500 |
barrels / day |
| No.2 Gas Oil Hydrodesulfurization Unit |
25,000 |
barrels / day |
| Vacuum Gas Oil Hydrodesulfurization Unit |
21,000 |
barrels / day |
| Hydrogen Producing Unit |
350,000 |
m3N / day |
| No.2 Hydrogen Producing Unit |
1,200,000 |
m3N / day |
| Fluid Catalytic Cracking Unit |
24,000 |
barrels / day |
| FCCGasoline Hydrodesulfurization Unit |
14,000 |
barrels / day |
| ETBE Unit |
1,850 |
barrels / day |
| Alkylation Unit |
8,000 |
barrels / day |
| No.2 Sulfur Recovery Unit |
70 |
t / day |
| No.3 Sulfur Recovery Unit |
70 |
t / day |
| No.4 Sulfur Recovery Unit |
150 |
t / day |
| Tail Gas Treating Unit |
356,000 |
m3N / day |
| Gasoline Splitter |
7,600 |
barrels / day |
| Delayed Coker Unit |
25,000 |
barrels / day |
| UOP Coker Naphtha Distilate Unionfining Unit |
42,000 |
barrels / day |
Power Facilities |
| Boilers |
4units |
268t / hour |
| Steam Turbine Generator |
1unit |
4,640kW |
| Power Receiving Equipment |
1unit |
14,000kVA |
| Power Receiving Equipment |
1unit |
12,500kVA |
| Power Receiving Equipment |
1unit |
30,000kVA |
| Power Receiving Equipment |
1unit |
40,000kVA |
| Co-generation Unit |
|
17,000kW |
Oil Storage Facilities |
| Crude Oil Tanks |
8units |
737,730kl |
Finished Product/ Semi-processed Product Tanks |
86units |
946,644kl |
| Sulfur Tanks |
2units |
2,400kl |
| Asphalt Tanks |
1unit |
3,100kl |
| LPGTanks |
27units |
48,933kl |
Port Facilities |
| Crude Oil Tanker Berth |
1unit |
259,999DWT |
| Loading / Unloading Piers |
7units |
|
End of main content